SCANNERS INSTALLATION - PILING AND CIVILS WORKS
Cotecna Inspection SA Senegal |
|
2009 |
8 Mths |
1.4 |
| |
Carried out all civils works for deep foundations for the subsequent installation of two X-Ray scanners and construction of three related administration, operations and control unit offices. The project was located in the Dakar harbour area. |
|
|
|
|
 |
|
|
|
 |
AHS IMPORT/EXPORT CARGO WAREHOUSE
AHS Menzies (GH) Limited Ghana |
|
2008 |
9 Mths |
4 |
| |
The EPC project comprises the detailed engineering, procurement and construction of a cargo warehouse at the Kotoka International Airport - Accra - Ghana. The warehouse some 9m high includes a mezzanine floor for offices. Included within the structure are cargo storage areas, with separate import and export facilities, offices, cold rooms, toilet facilities. The provision of and connection top all associated utilities is included in the project. |
|
|
|
|
 |
|
|
|
 |
RESIDENCE DE LA PAIX
Mixta Spain Senegal |
|
2007 |
15 Mths |
2.4 |
| |
Construction in Dakar of five residential apartment blocks, one comprising ground floor plus two floors and four with ground floor plus three floors, providing totally 80 apartments. |
|
|
|
|
 |
|
|
|
 |
EXTENSION TO MAIN TERMINAL LEOPOLD SEDAR SENGHOR AIRPORT
Administration des Activities Aeoronautiques National du Senegal (ASECNA) Senegal |
|
2006 |
15 Mths |
32.14 |
| |
This major refurbishment project for the airport comprised runway extensions and resurfacing, the provision of all required ground lighting and additional navigational aids, extensive renovation and addition of 5000 sq.m to the main terminal building including air-cooled chilled water plant and diesel power plant with associated step up/step down transformers and medium voltage transmission to the terminal building. Renovation of existing departure area facility, construction of additional parking areas with access roads, security access and lighting, service buildings for car rental agencies and banking facility, a freight hangar with associated office space. The project commenced in December 2006. The project originally planned for 6 months was extended during execution due to numerous additional requirements by the client. Zakhem was responsible for all building extensions and associated renovation works. |
|
|
|
|
 |
|
|
|
 |
SAI REPUBLIQUE BUILDING
SAI Republique Senegal |
|
2006 |
6 Mths |
1 |
| |
Rehabilitation and extension of a nine storey office building in Dakar city center, including excavation, construction of a raft foundation, concrete structural works, demolition, masonry works, all required finishing works and associated electrical & mechanical works. New build 1400 sq.m and renovation 2800 sq.m. |
|
|
|
|
 |
|
|
|
 |
PROJECT DE REAMENAGEMENT ET EXTENSION DE LA BRIGADE DE GENDARMARIE DE POPONGINE
Projet de Construction D'Immeubles Administratifs et de Rehabilitation du Patrimone Bati de L'Etat Senegal |
|
2004 |
6 Mths |
1.15 |
| |
Project for the construction of a police base in the town of Popongine near to the Presidential retreat, comprising the construction of five new single storey buildings and the rennovation of four existing buildings. |
|
|
|
|
 |
|
|
|
 |
RAINWATER RETENTION / DIVERSIONARY DAMS PROJECT
Ministere de L'Agriculture et de L'Elevage Senegal |
|
2003 |
2 Mths |
0.4 |
| |
This environmental related project for the construction of three small dams was carried out on an emergency basis in order to prevent the repetative loss of local village habitats & food stores and the regularly ensuing distress for the village population. In addition the the water retained by the dams provides a water source to help sustain local agriculture.
The basic earth fill dams with diversionary channels were constructed across naturally formed stormwater drainage channels and the project consisted of all excavation, foundation works, earth dam filling and compaction, reinforced concrete overspill channel walls and concrete bound rip rap facings.
Basic works were completed in 1.5 months and now additional works in the area are being considered by the client to further improve the effectiveness of the dams and provide additional protection from the environment for the local village.
Works were started mid June 2003. The initial contract works were completed and acceptance certificate issued on 24 July 2003. Additional works were carried out to enhance water retention and utilization and acceptance certificate issued on 8 October 2003. |
|
|
|
|
 |
|
|
|
 |
CONSTRUCTION OF THE LAT DIOR STADIUM - THIES
Project de Construction et de Rehabilitation Du Patrimoinede L'Etat (PCRPE) Senegal |
|
2003 |
18 Mths |
4.8 |
| |
The Contract for this project was signed on 21 October 2003 with PCRPE and comprises procurement, construction and Commissioning of the following works: i. Rehabilitation and extension of outdoor football stadium, ii Construction of indoor basketball and atheletics track, iii Provision of electrical network and floodlighting. The beneficiary of the project carried out under the direction of PCRPE is the Ministory of Sport. Project is now delayed after it was put on hold by the client in January 2005. |
|
|
|
|
 |
|
|
|
 |
UNIVERSITY OF FUTURE AFRICA
Project de Construction et de Rehabilitation du Patrimoinede L'Etat (PCRPE) Senegal |
|
2001 |
50 Mths |
20 |
| |
This prestigious turnkey project includes the preparation of feasability study, preparation of detailed building programs, detailed design of buildings, infrastructure & landscaping, final listing of furniture & equipment requirements. The preparation of the final project cost estimate. The construction of the project commencing with the infrastructure. Involved in assisting Client in setting up funding for the project. Works were proceeding steadily until works were suspended in 2006 by the client due to lack of available funds. |
|
|
|
|
 |
|
|
|
 |
ST GEORGES HOSPITAL EXTENSION - BEIRUT
St Georges Hospital Lebanon |
|
1997 |
18 Mths |
3 |
| |
The project for the construction of 35,000 sq.m., multi storey reinforced concrete framed structure providing, 400 patient bedrooms, 10 operating theatres, a morgue, classrooms, a computer center, coffee shop & dietary cafeteria, 9 diagnostic clinics, doctors clinics, emergency room trauma centre, catering facilities & standby power facilities. |
|
|
|
|
 |
|
|
|
 |
ROMANIAN EMBASSY - BEIRUT
Romanian Embassy Lebanon |
|
1996 |
24 Mths |
1.1 |
| |
Complete rehabilitation of embassy building. |
|
|
|
|
 |
|
|
|
 |
23-24 KENSINGTON GORE - LONDON
Wildlink Limited England |
|
1996 |
24 Mths |
6 |
| |
The project included the demolition of two existing houses and the construction of a reinforced concrete framed structure providing five luxury appartments over 6 levels, with basement carparking. The finishing works were to an extremely high standard and the building was fully airconditioned throughout. |
|
|
|
|
 |
|
|
|
 |
PALACE GATE RESTAURENT COMPLEX
Catering & Restaurents Limited England |
|
1995 |
3 Mths |
0.85 |
| |
The refurbishment and conversion of property into first class, fully air conditioned restaurent. |
|
|
|
|
 |
|
|
|
 |
UNIVERSITY - INN HOTEL
New Byblos City Inc Lebanon |
|
1995 |
26 Mths |
17 |
| |
Construction of 200 room, 4 star hotel. |
|
|
|
|
 |
|
|
|
 |
CASERNE ARMY CAMP
Ministry of Defence Lebanon |
|
1995 |
15 Mths |
1.5 |
| |
The project comprised the complete rhabilitation of the Caserne Army Camp at Abou Sleiman - Ablah |
|
|
|
|
 |
|
|
|
 |
KIPEVU STORAGE FACILITY
Kenya Pipeline Company Kenya |
|
1995 |
8 Mths |
0.5 |
| |
Repairs to fire hydrant system, repairing or replacing corroded elements of storage tanks and pipelines. |
|
|
|
|
 |
|
|
|
 |
NEW BYBLOS CITY DORMITORY BUILDINGS
New Byblos City Lebanon |
|
1994 |
35 Mths |
8.5 |
| |
The project comprised 2 No, 6 storey buildings, each with 200 rooms totalling 18,000 sq.m., including parking and shopping centre. |
|
|
|
|
 |
|
|
|
 |
REFURBISHMENT RIVIERA HOTEL - BEIRUT - PHASE LL
Riviera Hotel Limited Lebanon |
|
1994 |
9 Mths |
2.4 |
| |
Project for the extension and refurbishment of the hotel leisure center including the complete modernisation of the swimming pool located on sea front. |
|
|
|
|
 |
|
|
|
 |
BEIRUT UNIVERSITY COLLEGE - BYBLOS - PHASE LL
Beirut University College Lebanon |
|
1993 |
22 Mths |
3.5 |
| |
Project for the construction of new Architecture & Engineering inclusive of all related infrastructure works. |
|
|
|
|
 |
|
|
|
 |
REFURBISHMENT OF RIVIERA HOTEL - BEIRUT
Riviera Hotel Limited Lebanon |
|
1992 |
15 Mths |
4.7 |
| |
The project for the complete refurbishment of a 125 bedroom hotel with conference facilities and reception areas, providing air conditioning throughout. |
|
|
|
|
 |
|
|
|
 |
BEIRUT UNIVERSITY COLLEGE - BYBLOS
Beirut University College Lebanon |
|
1991 |
20 Mths |
5 |
| |
The project comprised the construction of a new general administration building and infrastructure works for the new University complex at Byblos |
|
|
|
|
 |
|
|
|
 |
RUA CARDEAL MERCIER DEVELOPMENT - LISBON
London & Lisbon Holdings Portugal |
|
1991 |
12 Mths |
3.2 |
| |
Construction of new mixed residential / commercial development comprising a reinforced concrete framed structure providing 16 luxury appartments, office units at ground floor level & two levels of underground car parking. |
|
|
|
|
 |
|
|
|
 |
QUEENSGATE MEWS - LONDON
Sunford Corporation England |
|
1991 |
3 Mths |
0.55 |
| |
Erection of shell unit for new residential building. |
|
|
|
|
 |
|
|
|
 |
HARCOURT STREET LONDON
Zakhem Properties Limited England |
|
1991 |
5 Mths |
0.28 |
| |
Extensin and refurbishment of existing "Listed Buildng" into residential units with retail / commercial units at ground and basement levels. |
|
|
|
|
 |
|
|
|
 |
COPTHORNE HOTEL - SLOUGH
Copthorne Hotels (Slough) Limited England |
|
1989 |
17 Mths |
31 |
| |
Construction of a 219 room, 9 storey hotel with conference facilities including two levels of underground parking for up to 300 cars. The project was completed in just over 17 months using the "Tunnel Form" method of contruction for the main reinforced concrete frame. Prefabricated bathroom pods were utilised throughout. Included in the project was the complete fitting out of the hotel which incorporated the latest technology in M & E control systems and computer based operational facilities and environment control. |
|
|
|
|
 |
|
|
|
 |
QUEENS GATE MEWS - LONDON
Zakhem Properties Limited England |
|
1988 |
4 Mths |
0.25 |
| |
Total refurbishment of existing house into a three bedroom luxury mews house with integral garage. |
|
|
|
|
 |
|
|
|
 |
REFURBISHMENT OXFORD STREET / COPTIC STREET - LONDON
Palmcourt Limited England |
|
1987 |
10 Mths |
1.2 |
| |
Refurbishment of two existing buildings forming an "L" shaped site into luxury flats on three floors with retail / commercial units at ground floor & basement levels. |
|
|
|
|
 |
|
|
|
 |
BUILDING - EARLS COURT ROAD - LONDON
Palmcourt Limited England |
|
1986 |
6 Mths |
0.77 |
| |
The project for the construction of a reinforced concrete framed building in Earls Court Road and included residential and commercial development on three floors with basement and ground floor office facilities. |
|
|
|
|
 |
|
|
|
 |
KIPEVU POWER STATION
Kenya Power Company Kenya |
|
1986 |
12 Mths |
0.4 |
| |
Project for all the civils works relating to the substructures of the power station. |
|
|
|
|
 |
|
|
|
 |
COPSE HILL HOUSING - WIMBLEDON
Zakhem Properties Limited England |
|
1985 |
14 Mths |
3 |
| |
The project situated in the Wimbledon area of London comprised the construction of 5 No 2,500 sq.ft secluded, luxury terraced houses each with an integral garage and on an adjacent site the two large luxury detached houses with separate detached double garages. The works included all services and infrastructure works. |
|
|
|
|
 |
|
|
|
 |
REINSTATEMENT WORKS TO PIPELINE RIGHT OF WAY
Kenya Pipeline Company Kenya |
|
1985 |
6 Mths |
0.5 |
| |
General reinstatement works to the Mombasa - Nairobi Oil Pipeline right of way. |
|
|
|
|
 |
|
|
|
 |
MALABA STATION DEPOT - PHASE L
Kenya Railways Kenya |
|
1985 |
12 Mths |
2.5 |
| |
Project comprised the construction of all buildings, roads, carpark, sewage system and all other associated civils works. |
|
|
|
|
 |
|
|
|
 |
FRESH WATER TANK - KIGAMBONI
Tazama Pipeline Company Limited Tanzania |
|
1985 |
6 Mths |
0.4 |
| |
Construction of a fresh water, reinforced concrete, storage tank including all piping installation and pump house. |
|
|
|
|
 |
|
|
|
 |
RECREATION CENTER
Britih Petroleum Tanzania |
|
1985 |
6 Mths |
0.6 |
| |
Project for the complete construction of a recreation centre including club house, cafeteri and other amenities. The pproject included all external work and landscaping. |
|
|
|
|
 |
|
|
|
 |
FOREST PARK DEVELOPMENT - ALGARVE
Quinta da Colina Sociedade Urban Izadora LDA Portugal |
|
1985 |
36 Mths |
18 |
| |
This was a prestigious design and construct project comprising the development of over 300 acres into residential, commercial & leasure facilities. The project included an 18 hole championhip level golf course and all infrastructure works. Over 100 luxury villas, tourist houses, a clubhouse and swimming pools were constructed under Phase l of this project. |
|
|
|
|
 |
|
|
|
 |
KENYA RAILWAY TELECOMMUNICATIONS PROJECT PHASE LL
Kenya Railways / Phillips GmBH Kenya |
|
1985 |
14 Mths |
1.45 |
| |
Civil works project comprising trenching and laying telecommunications cables along the Mombasa to Nairobi railway line. A total of 525 kms. |
|
|
|
|
 |
|
|
|
 |
UMOJA PHASE LL PROJECT - HOUSING SCHEME CIVIL WORKS.
Ministry of Housing Nigeria |
|
1985 |
6 Mths |
0.5 |
| |
Earth works for housing project, heavy excavation of black cotton soil & rock |
|
|
|
|
 |
|
|
|
 |
INTERCONTINENTAL HOTEL - MOMBASA
Equatorial Beach Properties Limited Kenya |
|
1984 |
22 Mths |
17 |
| |
Management Contractor for the contruction and complete fitting out of a 200 room, 5 star hotel with all retaurants, public facilities, health club & gambling casino. |
|
|
|
|
 |
|
|
|
 |
ELISA COURT DEVELOPMENT - LONDON
Zakhem Properties Limited England |
|
1984 |
18 Mths |
2.6 |
| |
The project situated in Chitty Street, Central London for the construction of a totally new building spanning Charlotte Mews and comprised basement offices, ground floor showrooms and 16 No luxury flats on the 1st to 4th floors. |
|
|
|
|
 |
|
|
|
 |
LAMBOURNE AVENUE HOUSING COMPLEX - WIMBLEDON
Zakhem Properties Limited England |
|
1984 |
15 Mths |
3.2 |
| |
The project comprised the construction of 6 No luxurious, large detached houses each with an area of 3,500 sq.ft., including complete infrastructure/services, landscaping and all associated structures. |
|
|
|
|
 |
|
|
|
 |
OFFICE BUILDING - OLD BROMPTON ROAD
Zakhem Properties Limited England |
|
1983 |
24 Mths |
4 |
| |
The project for the complete construction of a modern mixed function, office - residential building in south west London. The building included office space on ground and lower ground floor, 24 residential appartments on the 1st to 5th floor. Also underground parking for 27 vehicles was provided. |
|
|
|
|
 |
|
|
|
 |
ZAKHEM PLAZA - BEIRUT
Zakhem Engineers SAL Lebanon |
|
1983 |
24 Mths |
10 |
| |
Project for the complete construction of an ultra modern, multi storey office tower complete with ground level shopping arcade and underground, basement car parking. |
|
|
|
|
 |
|
|
|
 |
RESIDENTIAL CONDOMINIUM - ARLINGTON - TEXAS
Cedarland Development Company United States of America |
|
1983 |
24 Mths |
15 |
| |
The project comprised the construction of residential condiminiums, a shopping centre and commercial buildings. |
|
|
|
|
 |
|
|
|
 |
RECREATIONAL FACILITIES MADHAB FALEJ & FUJAIRA
Ministry of Agriculture & Fisheries United Arab Emirates |
|
1982 |
10 Mths |
1.5 |
| |
The project comprised the complete landscaping and irrigation wporks for the area and included two swimming pools, two saunas, a childrens park and general development of the Falej area. In addition the project included the drilling of two water wells, the supply & installation of submersible pumps in the wells, the construction of a 250 cu.m reinforced concrete water tank and connection pipework from the well to storage tank. |
|
|
|
|
 |
|
|
|
 |
CHARTERED BANK - DOHA
Chartered Bank Qatar |
|
1981 |
15 Mths |
10 |
| |
Project for the complete contruction of a ultra modern head office building. |
|
|
|
|
 |
|
|
|
 |
NEW WOMENS HOSPITAL - HAMAD GENERAL HOSPITAL - PHASE L
Ministry of Public Works Qatar |
|
1981 |
4 Mths |
0.9 |
| |
Project for all groundworks and foundations related to the new facilities. |
|
|
|
|
 |
|
|
|
 |
ENDELL STREET HOSTEL
Wiseprest Limited England |
|
1980 |
10 Mths |
1.4 |
| |
Refurbishment of 167 bed youth hospital in London. Works included the basement, kitchen & dining areas, the wardens flat and the ground floor reception area. |
|
|
|
|
 |
|
|
|
 |
OAK CENTER OFFICE PARK
Cedarland Development Company United States of America |
|
1980 |
12 Mths |
4.7 |
| |
General office park development containing office units and including intallation of all utilities. |
|
|
|
|
 |
|
|
|
 |
RECREATIONAL FACILITIES - DUKHAN
Qatar General Petroleum Company Qatar |
|
1980 |
12 Mths |
2 |
| |
Project comprised the construction of cinema and sports facilities. |
|
|
|
|
 |
|
|
|
 |
MEDICAL STAFF ACCOMODATION FOR HAMAD GENERAL HOSPITAL
Ministry of Health Qatar |
|
1980 |
24 Mths |
20 |
| |
Project for the construction of accomodation units to house hospital staff. |
|
|
|
|
 |
|
|
|
 |
NEW HEADQUARTERS - QATAR INSURANCE COMPANY
Qatar Insurance Company Qatar |
|
1980 |
18 Mths |
6.5 |
| |
Project for the complete construction of office building. |
|
|
|
|
 |
|
|
|
 |
WATER SUPPLY STORAGE TANK - SHARJAH
Government of Sharjah United Arab Emirates |
|
1978 |
8 Mths |
0.2 |
| |
Complete construction of water storage tank. |
|
|
|
|
 |
|
|
|
 |
JAIDAH TOWER DEVELOPMENT
Jaidah Motors & Trading Company Qatar |
|
1977 |
24 Mths |
8 |
| |
The project for the complete construction of a twin tower, 15 storey office building complete with central air conditioning and including all electrical / mechanical works. |
|
|
|
|
 |
|
|
|
 |
ALI BIN TALIB SCHOOL - SHARJAH
Government of Sharjah United Arab Emirates |
|
1977 |
6 Mths |
0.53 |
| |
Construction of school building complete with all associated works. |
|
|
|
|
 |
|
|
|
 |
VILLA CONSTRUCTION
Sheik Ali Salim United Arab Emirates |
|
1976 |
18 Mths |
1.6 |
| |
Project for the complete construction of 10 No luxury villas. |
|
|
|
|
 |
|
|
|
 |
AJMAN ARAB BANK TOWER BUILDING
Arab Bank - Ajman United Arab Emirates |
|
1976 |
15 Mths |
1 |
| |
Project for the construction of a multi storey office building including all works. |
|
|
|
|
 |
|
|
|
 |
POULTRY FARMS
Unifood - Sharjah United Arab Emirates |
|
1976 |
8 Mths |
0.65 |
| |
Construction of poultry farms. |
|
|
|
|
 |
|
|
|
 |
WAREHOUSE & SHOWROOMS
Harrisons - Dubai United Arab Emirates |
|
1976 |
8 Mths |
0.5 |
| |
Project for the complete construction of a warehouse & showroom. |
|
|
|
|
 |
|
|
|
 |
PREFABRICATED HOUSING FACTORY - TRIPOLI
Ministry of Housing Libya |
|
1974 |
12 Mths |
2.5 |
| |
The project for all civil works, mechanical erection and installation of utilities (both electrical and water) for a prefabricted housing factory complex included sheds, factory and administration building.
(Excluding the supply of materials.) |
|
|
|
|
 |
|
|
|
 |
GAS STATIONS - QATAR
Ministry of Petroleum Qatar |
|
1973 |
30 Mths |
2.8 |
| |
Project comprised the civil works for the construction of all required foundations for 10 No gaseline stations. Works were staggered over 30 months to suit the Clients requirements. |
|
|
|
|
 |
|
|
|
 |
DIDDEH RESIDENTIAL SCHEME
Zakhem Real Estate Lebanon |
|
1972 |
12 Mths |
1 |
| |
Project comprised 10 No appartment buildings and included all works. |
|
|
|
|
 |
|
|
|
 |
SOCIAL SECURITY BUILDING BAGHDAD
Directorate of Social Security Iraq |
|
1967 |
30 Mths |
2.6 |
| |
The project for an office building with area of 29,500 sq.m, the location in central Bagdad in a built up area. Works were staggered over 30 months to suit the client. |
|
|
|
|
 |
|
|
|
 |
KATCHAKU & MANDHI BAHAUDDINE HOUSING SCHEME
Katchaku & Mandhi Housing Department Pakistan |
|
1963 |
24 Mths |
1.8 |
| |
Project for 500 housing units. |
|
|
|
|
 |
|
|
|
 |
VIHARI HOUSING SCHEME
Vihari Housing Department Pakistan |
|
1962 |
24 Mths |
2.5 |
| |
The project, situated in the Indus Basin, comprised the construction of two housing colonies with a total of 400 homes. |
|
|
|
|
 |
|
|
|
 |
 |
 |
 |
|
|
|
 |
|
|
|
|
 |
EDEN ROCK
Hardstand SA Senegal |
|
2008 |
24 Mths |
15.6 |
| |
Construction of three high standard VIP residential blocks each with 8 floors. The project located in the center of Dakar near to the beach comprised the luxurious apartment blocks plus underground parking facilities and four swimming pools. The contract was singed on 23 June 2008. |
|
|
|
|
 |
|
|
|
 |
KEMPINSKI ACCRA HOTEL
Gold Coast City Resorts Limited Ghana |
|
2007 |
24 Mths |
46.5 |
| |
This EPC contract for a 249 room 5 star hotel situated on a prime site in the centre of Accra includes initial feasability studies, design/detailed engineering, procurement of all construction materials/hotel furnishings and equipment. Both detailed design and construction are now underway. Construction works include site clearance and construction of infrastructure providing all required utilities\services, construction of the 7 storey concrete framed structure including bedrooms, leasure facilities, bars, restaurents and staff facilities. The Engineering works are being executed in the USA under the supervision of Zakhem Construction. |
|
|
|
|
 |
|
|
 |
|
|
|